I-40 Rock Slide

upnover

Grumpy, decrepit Old Man
Moderator
Joined
Mar 20, 2005
Location
Morganton NC
I-40 reopening delayed a month
By Steve Lyttle
slyttle@charlotteobserver.com
Posted: Tuesday, Feb. 23, 2010



Citing extremely harsh weather, North Carolina transportation officials said Tuesday afternoon that Interstate 40 near the Tennessee border won’t be reopened until late April.


That is a month later than had been expected.


Crews have been working for nearly four months to repair a section of I-40 damaged in a large rock slide last Oct. 25. The project has included installing large metal bolts into the mountainside along I-40, to prevent additional problems.


But the mountain area has received 2 1/2 times its average annual snowfall, and officials say 17 inches of rain has fallen in the area since December.


“This has been an incredibly harsh winter, and because of that, the specialty contractors have not been able to do as much work as planned,” said Jon Nance, chief engineer of operations for the N.C. Department of Transportation.


Nance said the bad weather has allowed engineers to discover five additional sites that need work. Four of those sites are west of where the rock slide took place -- in other words, closer to the Tennessee border. The five site is about 1 1/2 miles east of where the rock slide took place. All five sites are on the portion of I-40 that is closed, so the additional repairs will not affect motorists.


Even when the highway is reopened, engineers say, one lane on the westbound side will remain closed until this summer so crews can complete installing the bolts and anchor mesh.


Nance said crews have taken advantage of the closure on I-40 to take on an additional $5.3 million in maintenance work. That includes:


-- Paving and maintenance of three tunnels within the closed section of the highway.


-- Repairs and maintenance to four bridges, include the bridge over White Oak Road in Haywood County.


-- Tree and brush maintenance and slope-mowing.
 
The vehicles traveling through the area are disturbing the rock beds too much. Road Closed until further studies can be conducted.
 
“This has been an incredibly harsh winter, and because of that, the specialty contractors have not been able to do as much work as planned,”


Nance said the bad weather has allowed engineers to discover five additional sites that need work.
So the engineers are working in the bad weather but the specialty contractors aren't?


Is there a good, short detour around the closed area?
How long of a delay can I expect when traveling through that stretch?
Went from Dallas to Alcoa (SW of Knoxville) on saturday, took 3hr45min, normally takes about 3hr25min. We took I26 north of Asheville to 25/70, and then connected back to 40 in TN. Was a nice drive through the country.

On the return trip I went 40E to 81N to 26S, took about 4hr30min. But I was driving a vehicle with no clutch, so I didn't want to have to stop.
 
In my opinion, it couldn't have happened at a better time! If anybody ever stoped to look at the bridges in that stretch, they'd stop driving on them.
Much needed bridge maint, that wasn't gonna happen while the road was open!
 
I'm betting they'll postpone it once maybe twice more by the time its actually opened. And this line equates into a huge gawkfest/traffic jam that will make it quicker to take a bypass still-"Even when the highway is reopened, engineers say, one lane on the westbound side will remain closed until this summer so crews can complete installing the bolts and anchor mesh."
 
yeah x2 on the 70/25 (through hot springs NC and Newport TN.)don't take the truck route up and around Johnson city it takes forever. from Newport take 321 south if you want to get back to gatlinburg area.

You could also 441 through the park from gatlinburg to cherokee if the pass is open. closed alot this time of year because of snow though.if your lookin to stay on 40 take the 70/25.
 
Back
Top