Building code & Engineered footings???

So the rebar is drilled through the pole? If so, it’s to anchor the 6x6 into the concrete, much like Nelson studs on a steel post.

What size rebar? I’d think #5 or 6.

I’d make sure to pump out and keep that hole dry. Otherwise the water will soften the subgrade and could allow for some settling over time.
 
So the rebar is drilled through the pole? If so, it’s to anchor the 6x6 into the concrete, much like Nelson studs on a steel post.

What size rebar? I’d think #5 or 6.

I’d make sure to pump out and keep that hole dry. Otherwise the water will soften the subgrade and could allow for some settling over time.

#4 rebar drilled through the post.

Holes are dry as of now, trying to get the inspector back to have them so we can get the 6” base poured.


Sent from my iPhone using Tapatalk
 